RU | EN
      1. 3.2.1 Network Exploitation and Grid Asset Consolidation
      2. 3.2.2 Connection
      3. 3.2.3 Electricity Transmission
      4. 3.2.4 Additional (non-tariff) services
      5. 3.2.5 Consumer liaison
      6. 3.2.6 Key RAS metrics
      7. 3.2.7 Key IFRS metrics
      8. 3.2.8 Tariff Policy
      9. 3.2.9 Investments
      10. 3.2.10 Innovations

For the operation of the site, we collect cookies, information about the IP address and location of users. If you do not want this data to be processed, please leave the site.

3.2.9 Investments

The PAOPublic Joint-Stock Company Rosseti Ural’s investment program for 2025 was adopted by the Ministry of Energy[26].

The Company’s 2023-2025 cost and physical parameters

Parameter 2023 2024 2025 2025/2024, %
Funding, RUBruble million plus VATvalue-added tax 20,239 19,494 17,970 -8%
Capex, RUBruble million net of VATvalue-added tax 16,089 16,081 17,960 12%
New fixed assets, RUBruble million net of VATvalue-added tax 14,446 16,834 18,652 11%
Commissioning of transformer capacity, MVA 1,652 832 846 2%
Commissioning of power lines, km 7,605 1,780 2,404 35%

Implementation of the investment program includes handling of the following problems:

Investment funding structure in 2023-2025:

Parameter 2023 2024 2025 2025/2024, %
Total: 20,239 19,494 17,970 -8%
Connection 11,475 11,367 10,019 -12%
Reconstruction, upgrade and retrofitting 5,784 5,200 4,858 -7%
Investment projects, implemented under energy sector perspective development schemes and programs 163 311 42 -87%
Other greenfield construction of energy facilities 182 352 149 -58%
Purchase of land plots for investment projects 0 0 13 no data
Other investment projects 2,636 2,264 2,890 28%

The bulk of the 2025 funding (56%) was channeled to connection. Investments spent on reconstruction, upgrade and retrofitting totaled 27%. A 16% share of the total funding was spent on other investment projects (ready-to-operate devices, IT projects, etc.), funding of the investment projects, implemented under the energy sector perspective development schemes and programs totaled 0.2%; funding on greenfield construction totaled 1%. As for the sources of financing, the Company’s internal funds contributed the most to the total funding (98% or RUBruble 17,683 million). Raised funds totaled RUBruble 287 million or 2%. We have no state-funded projects.

The largest investment projects completed in 2025

Region Title of an investment project Goals Commissioning in 2025
Perm region Construction of substation 10/0.4 kV and metering equipment, 10 kV cable line to provide electricity supply to an oncologic clinic (6.28 MVA, 6 kV cable line: 2.7 km) Development of the electric grids (execution of a contract on connection) 202.46
Perm region Reconstruction of 110 kV Yayiva GRES – Solikamsk I, II chain power line (110 kV power line: 14.422 km) Development of the electric grids (Renovation of PAOPublic Joint-Stock Company Rosseti Ural Grids in 2024-2028 Program[27]). 241.51
Perm region Construction of a branch line to 110 kV Yuzhnyi Rudnik substation with the installation of the branch support from 110 kV Titan – Solikamsk I, II chain power line (110 kV power line: 1.801 km) Development of the electric grids (execution of a contract on connection) 67.39
Sverdlovsk region Reconstruction of 110 kV Alapayevsk substation (installation of 3 additional 110 kV sections and 3 relay protection devices). Construction of 110 kV Alapayevsk – Sphera I, II chain power line (110 kV power line: 2.215 km; 110 kV cable line: 1.442 km) Development of the electric grids (execution of a contract on connection and agreement on compensation) 455.58
Sverdlovsk region Construction of 10kV distribution line to provide electricity supply to UrFU campus – Digital Transformation Center FGAOUVO UrFU named after B.N. Yeltsyn (16 MVA; 1 10 kV cable line: 7.6 km) Development of the electric grids (execution of a contract on connection) 310.24
Sverdlovsk region Reconstruction of 110 kV PS Svarochnaya — PS Daurskaya power line, 110 kV PS Svarochnaya – PS Elektromed power line, 110 kV PS Svarochnaya — PS Pyshma power line. Reconstruction of a 110 kV power line at the intersection with railway tracks (110 kV powerline: 1.34 km) Development of the electric grids (agreement on compensation of expenses on grid facilities repositioning) 348.36
Chelyabinsk region Reconstruction of 110 kV Ufaley – Mramornaya 2 power line, 110 kV Ufaley – Mramornaya 3 power line (replacement of support and wire), reconstruction of 110 kV Ufaley substation (replacement of busbar and RPArelay protection automation devices), City of Verkhniy Ufaley (110 kV power line: 9 km, 6 RPArelay protection automation devices) Development of the electric grids (agreement on compensation) 220.18
Chelyabinsk region Reconstruction of 110 kV Yesaulka substation (replacement of power transformers from 2х10 MVA to 2х25 MVA, 2 110 kV circuit breakers) Development of the electric grids (execution of a contract on connection) 64.58

Long-term investment program

Cost and physical parameters 2026 2027 2028 2029
Funding, RUBruble million, incl VATvalue-added tax 23,945 16,862 17,315 16,318
Capex, RUBruble million net of VATvalue-added tax 21,490 11,945 14,556 12,456
New fixed assets, RUBruble million net of VATvalue-added tax 21,744 12,546 15,144 12,183
Commissioning of transformer capacity, MVA 706 123 125 123
Commissioning of power lines, km 2,806 1,157 1,183 861

The PAOPublic Joint-Stock Company Rosseti Ural’s investment program for 2026-2029 was adopted by the Ministry of Energy[26]. The Company’s investment program for 2026-2029 stipulates RUBruble 74,439 million (incl. VATvalue-added tax) funding, RUBruble 60,447 million (net of VATvalue-added tax) capex and RUBruble 61,616 million (net of VATvalue-added tax) new fixed assets. The Company’s 2026-2029 investment program is prepared with due allowances to regional development plans, equipment health, importance of grid facilities and current domestic environment.